MIS LOG IN

NPRR380

Summary

Title Minor Changes to Default Uplift Invoice
Next Group
Next Step
Status Approved on 09/20/2011
Effective Dates
10/01/2011

Action

Date Gov Body Action Taken Next steps
09/20/2011 BOARD Approved
08/04/2011 TAC Recommended for Approval Board of Directors consideration
07/21/2011 PRS Recommended for Approval TAC consideration
06/23/2011 PRS Recommended for Approval PRS review the IA.

Voting Record

Date Gov Body Motion Result
09/20/2011 BOARD To approve NPRR380 as recommended by TAC in the 8/4/11 TAC Report. Passed
08/04/2011 TAC To recommend approval of NPRR380 as recommended by PRS in the 7/21/11 PRS Report and as amended by the 7/27/11 ERCOT comments Passed
07/21/2011 PRS To endorse and forward the 6/23/11 PRS Report and Impact Analysis for NPRR380 to TA Passed
06/23/2011 PRS To recommend approval of NPRR380 as submitted. Passed

Background

Status: Approved
Date Posted: Jun 8, 2011
Sponsor: ERCOT
Urgent: No
Sections: 9.19.1
Description: This Nodal Protocol Revision Request (NPRR) provides minor corrective and clarifying changes to the allocation methodology used for the Default Uplift Invoice.
Reason: Modifications are necessary because the current Protocol formula does not appropriately convert the Qualified Scheduling Entity (QSE) Energy Trades to MWh prior to use in the allocation formula. Additionally, the allocation formula was re-organized for ease of use and to provide additional data points that can be used for analysis.

Key Documents

Related Content