NPRR1037

Summary

Title Correction to the Settlement of Switchable Generation Resources (SWGRs) Instructed to Switch to ERCOT
Next Group
Next Step
Status Approved on 10/13/2020
Effective Dates
11/01/2020

Action

Date Gov Body Action Taken Next steps
10/13/2020 BOARD Approved
09/23/2020 TAC Recommended for Approval Revision Request Consideration
09/10/2020 PRS Recommended for Approval Revision Request Consideration
08/13/2020 PRS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
10/13/2020 BOARD to approve NPRR1037 as recommended by TAC in the 9/23/20 TAC Report Passed
09/23/2020 TAC to recommend approval of NPRR1037 as recommended by PRS in the 9/10/20 PRS Report Passed
09/10/2020 PRS to endorse and forward to TAC the 8/13/20 PRS Report and Impact Analysis for NPRR1037 Passed
08/13/2020 PRS to recommend approval of NPRR1037 as submitted Passed

Background

Status: Approved
Date Posted: Jul 29, 2020
Sponsor: ERCOT
Urgent: No
Sections: 6.6.12.1
Description: This Nodal Protocol Revision Request (NPRR) provides a correction to the settlement of Switchable Generation Resources (SWGRs) when instructed by ERCOT to switch from a non-ERCOT Control Area to the ERCOT Control Area. Specifically, this NPRR includes “Operational Costs” (“OPCs”) incurred by the SWGR in the non-ERCOT Control Area in the calculation of the “Switchable Generation Operating Cost” (“SWOC”) for Resources with approved verifiable costs. OPC is currently included only for Resources without approved verifiable costs.
Reason: Addresses current operational issues