MIS LOG IN

NPRR295

Summary

Title Synchronization of Protocol for Generation Resource Designation as Mothballed or Decommissioned
Next Group
Next Step
Status Approved on 12/14/2010
Effective Dates
12/14/2010

Action

Date Gov Body Action Taken Next steps
12/14/2010 BOARD Approved
12/06/2010 TAC Recommended for Approval BOD consideration
11/18/2010 PRS Recommended for Approval TAC consideration

Voting Record

Date Gov Body Motion Result
12/14/2010 BOARD To approve NPRR295 as recommended by tac in the 12/6/10 tac report with an effective date of "upon ercot board approval Passed
12/06/2010 TAC To recommend approval of NPRR295 as recommended by PRS in the 11/18/10 PRS Report, to grant NPRR295 Urgent status, and to direct WMS to review the issues set forth in the 12/3/10 Topaz Power comments Passed
11/18/2010 PRS To recommend approval of NPRR295 as submitted and to forward NPRR295 and the Impact Analysis to TAC. Passed

Background

Status: Approved
Date Posted: Nov 11, 2010
Sponsor: ERCOT
Urgent: Yes
Sections: 2.1, 3.14.1.9, 22, Attachment H:
Description: This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with zonal Protocol Section 6.5.9.3, Generation Resource Return to Service Updates, regarding return-to-service of Mothballed or Decommissioned Generation Resources. In addition, a clarification was made for removal of Decommissioned Generation Resources from ERCOT registration systems.
Reason: Language in Section 3.14.1.9, specifying the treatment of Mothballed or Decommissioned Generation Resources, is insufficient in the Nodal Protocols and does not align with current zonal requirements.

Key Documents

Related Content