M-E110525-03 RTC+B: Implementation Details of Revision Requests
NOTICE DATE: December 3, 2025
NOTICE TYPE: M-E110525-03 Market Rules
SHORT DESCRIPTION: RTC+B: Implementation Details of Revision Requests
INTENDED AUDIENCE: All Market Participants
DAYS AFFECTED: December 5, 2025
LONG DESCRIPTION: On December 5, 2025, language associated with the following Revision Requests will be implemented for the Real-Time Co-optimization Plus Batteries (RTC+B) project. Unless otherwise noted, the Revision Request language will be fully implemented:
- NOGRR211, RTC - NOG 2 and 9: System Operations and Control Requirements and Monitoring Programs
- NOGRR221, Alignment Changes for January 1, 2021 Nodal Operating Guide - NPRRs 1010 and 1039
- NOGRR268, Related to NPRR1246, Energy Storage Resource Terminology Alignment for the Single-Model Era
- NOGRR276, Alignment Changes for June 1, 2025 Nodal Operating Guide - NPRR1246 and NPRR1270
- NOGRR277, Related to NPRR1282, Ancillary Service Duration under Real-Time Co-Optimization
- NOGRR278, Related to NPRR1290, Gap Resolutions and Clarifications for the Implementation of RTC+B
- NPRR963, Base Point Deviation Settlement and Deployment Performance Metrics for Energy Storage Resources (Combo Model)
- Sections 6.6.5.5, 6.6.5.5.1, and 6.6.5.6
- NPRR1000, Elimination of Dynamically Scheduled Resources
- NPRR1007, RTC - NP 3: Management Activities for the ERCOT System
- NPRR1008, RTC - NP 4: Day-Ahead Operations
- NPRR1009, RTC - NP 5: Transmission Security Analysis and Reliability Unit Commitment
- NPRR1010, RTC - NP 6: Adjustment Period and Real-Time Operations
- NPRR1011, RTC - NP 8: Performance Monitoring
- NPRR1012, RTC - NP 9: Settlement and Billing
- NPRR1013, RTC - NP 1, 2, 16, and 25: Overview, Definitions and Acronyms, Registration and Qualification of Market Participants, and Market Suspension and Restart
- NPRR1014, BESTF-4 Energy Storage Resource Single Model
- NPRR1029, BESTF-6 DC-Coupled Resources
- Sections 25.5.2, 25.5.5, and 25.5.6
- NPRR1046, Additional Revisions to Remove Dynamically Scheduled Resource (DSR) from the Protocols
- NPRR1075, Update Telemetered HSL and/or MPC for ESRs in Real-Time to Meet Ancillary Service Resource Responsibility
- NPRR1172, Fuel Adder Definition, Mitigated Offer Caps, and RUC Clawback
- Section 5.7.2
- NPRR1204, Considerations of State of Charge with Real-Time Co-Optimization Implementation
- NPRR1216, Implementation of Emergency Pricing Program
- Phase 1
- NPRR1236, RTC+B Modifications to RUC Capacity Short Calculations
- NPRR1245, Additional Clarifying Revisions to Real-Time Co-Optimization
- NPRR1246, Energy Storage Resource Terminology Alignment for the Single-Model Era
- NPRR1268, RTC - Modification of Ancillary Service Demand Curves
- NPRR1269, RTC+B Three Parameters Policy Issues
- NPRR1270, Additional Revisions Required for Implementation of RTC
- NPRR1282, Ancillary Service Duration under Real-Time Co-Optimization
- NPRR1290, Gap Resolutions and Clarifications for the Implementation of RTC+B
- Phase 1
- OBDRR020, RTC - Methodology for Setting Maximum Shadow Prices for Network and Power Balance Constraints
- OBDRR052, Related to NPRR1246, Energy Storage Resource Terminology Alignment for the Single-Model Era
- PGRR118, Related to NPRR1246, Energy Storage Resource Terminology Alignment for the Single-Model Era
- VCMRR044, RTC+B - Mitigated Offer Cap for Hydro Generation Resources
Please review the ERCOT website for previous Market Notices related to this subject.
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at ClientServices@ercot.com.
If you are receiving email from a public ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.
dg