NOTICE DATE: March 2, 2023
NOTICE TYPE: W-B030223-01 Operations
SHORT DESCRIPTION: New version of Resource Interconnection Handbook posted
INTENDED AUDIENCE: Resource Entities, Interconnecting Entities, and Transmission/Distribution Service Providers
DAYS AFFECTED: March 3, 2023
LONG DESCRIPTION: An updated Resource Interconnection Handbook, version 1.94, has been posted to the Resource Integration page on ERCOT.com. This version includes:
- Updates to various sections on requesting an FIS with the latest version of RIOO-IS with Substation Details
- RIOO-IS starting a new request as either an IE or a RE
- Replacing the term "RARF" with "resource data" or similar terms
- Change to the weatherization reference document
- Diagram to show new telemetry required for co-located data center loads
- New paragraph on Operation Requirements for Data Center load and/or PUN loads with IRR Generation
New appendices have been added to show:
- Appendix N to show Resource Status Codes taken from the ICCP Handbook 2020
Other general edits are also included.
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at ClientServices@ercot.com.
If you are receiving email from a public ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.
dg