NOTICE DATE: January 16, 2026
NOTICE TYPE: M-D011626-01 NPRR
SHORT DESCRIPTION: Implementation Details of PGRR131, Requirements for Interconnection Cost Reporting for Transmission-Connected Generators
INTENDED AUDIENCE: All Market Participants
DAYS AFFECTED: February 1, 2026
LONG DESCRIPTION: On February 1, 2026, Planning Guide language associated with Planning Guide Revision Request (PGRR) 131, Requirements for Interconnection Cost Reporting for Transmission-Connected Generators, will be implemented.
PGRR131 implements mandatory reporting requirements for Transmission Service Providers (TSPs) and ERCOT for interconnection cost reporting for transmission-connected generators pursuant to paragraph (i) of P.U.C. Subst. R. 25.195, Terms and Conditions for Transmission Service, and deletes greybox language superseded by the requirements.
ADDITIONAL INFORMATION: In accordance with Planning Guide Section 1.2.5, Planning Guide Revision Implementation, ERCOT provides notice as soon as practicable but no later than ten days prior to implementation.
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at ClientServices@ercot.com.