NOTICE DATE: April 29, 2026

NOTICE TYPE: M-B042926-01 Operations

SHORT DESCRIPTION: Reminder: Interconnecting TSPs to submit Large Load data for Quarterly Stability Assessment by deadlines specified in Planning Guide 5.3.5(2)

INTENDED AUDIENCE: Interconnecting TSPs and Interconnecting Large Load Entities

DAYS AFFECTED: April 29, 2026

LONG DESCRIPTION: As required by Section 5.3.5 of the Planning Guide, ERCOT conducts a Quarterly Stability Assessment (QSA) every three months. This assessment evaluates the stability impact of all new large generators and generator modifications and all new Large Loads and Load modifications that are expected to energize within a specified three-month window.

Section 9.6 of the Planning Guide requires all new or modified Large Loads to be included in a QSA to be eligible for Initial Energization. To ensure each eligible Large Load is included in the QSA assessment cycle that corresponds to the Load's desired Initial Energization date, the Interconnecting TSP must submit all required information by the deadline specified in Planning Guide Section 5.3.5(2), as shown in the table below. This information includes the DWG Large Load Survey and corresponding dynamic model for all Large Computational Loads seeking Initial Energization in the indicated period.

 

Generator Initial Synchronization or Large Load Initial Energization Date

Last Day for an IE, Resource Entity, or TSP to meet prerequisites as listed in paragraphs (4) and (5) below

Completion of Quarterly Stability Assessment

Upcoming January, February, March

Prior August 1

End of October

Upcoming April, May, June

Prior November 1

End of January

Upcoming July, August, September

Prior February 1

End of April

Upcoming October, November, December

Prior May 1

End of July

 

ACTION REQUIRED: The Interconnecting TSP for each Large Load must submit all required data by the deadline specified in Planning Guide Section 5.3.5(2) that corresponds to the Large Load's Initial Energization date.