NOTICE DATE: March 21, 2025
NOTICE TYPE: M-A052125-01 NPRR
SHORT DESCRIPTION: Partial Implementation Details of NPRR1234, Interconnection Requirements for Large Loads and Modeling Standards for Loads 25 MW or Greater
INTENDED AUDIENCE: All Market Participants
DAYS AFFECTED: June 1, 2025
LONG DESCRIPTION: On June 1, 2025, Protocol language associated with Nodal Protocol Revision Request (NPRR) 1234 will be partially implemented.
NPRR1234 and the related Planning Guide Revision Request (PGRR) 115, Related to NPRR1234, Interconnection Requirements for Large Loads and Modeling Standards for Loads 25 MW or Greater, establish interconnection and modeling requirements for Large Loads.
Specifically, the language in the following sections will be implemented:
Section 2.1, Definitions
Section 2.2, Acronyms and Abbreviations
Section 3.15, Voltage Support
Section 3.15.3, Generation Resource Requirements Related to Voltage Support
The remainder of NPRR1234 and PGRR115 will be implemented at a later date.
ADDITIONAL INFORMATION: In accordance with Protocol Section 21.6, Nodal Protocol Revision Implementation, and Planning Guide Section 1.2.5, Planning Guide Revision Implementation, ERCOT provides notice as soon as practicable, but no later than ten days prior to implementation.
NPRR1234, PGRR115, and the associated documents can be found on the ERCOT website.
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at ClientServices@ercot.com.
If you are receiving email from a public ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.
dg