
|
PRESS RELEASE
April 16, 2008
|
TOPICS:
The Board of Directors approved eight protocol revisions and the 2007 financial statements at Tuesday’s monthly meeting.
The board also approved the Technical Advisory Committee’s plan for managing protocol content and revisions during implementation of the nodal market. The plan was created in response to stakeholder discussions regarding scope challenges to nodal delivery and how to assure full protocol delivery. The plan outlines a process to ensure transparency and certainty on what functionality will be available for Texas Nodal Market Implementation.
As defined by the process, once a scope issue is identified, the Transition Plan Task Force (TPTF) will immediately assess the issue and then assign it to one of three categories: 1) needed for nodal “go-live;” 2) approved for post go-live; or 3) deferred projects. ERCOT staff will review the recommendations and report to TPTF on cost and schedule, and then TPTF will follow its established processes.
Board Chair Mark Armentrout expressed his appreciation to the Technical Advisory Committee for reaching a compromise on managing items in the nodal protocols that may not have functionality as originally planned.
The nodal market redesign remains on schedule for the Dec. 1, 2008 launch with less than 20 weeks before the beginning of the 168-hour (24-hours for 7 days) readiness tests during September. Checkpoints are in place to ensure ongoing viability of the go-live date, said Jerry Sullivan, executive director of the market redesign, in the nodal update.
The nodal software is now into the ninth and final release, Sullivan said. The top risk continues to be the challenge of integrating multiple systems into the common information model. Regression testing is being employed to ensure that new code fixes do not adversely affect other code functionality.
ERCOT readiness status is acceptable, but staffing levels and procedures need improvement. Market participant readiness is an area of concern and is projected to go to “red” status due to insufficient training and readiness.
In other board action, the directors approved the following Protocol Revision Request (PRR) and Nodal Protocol Revision Requests (NPRR):
PRR 743, Transmission Congestion Rights (TCR) to Congestion Revenue Rights (CRR), was deferred back to the Technical Advisory Committee for further revisions to address how to handle refunds if the nodal market does not go live Dec. 1, 2008. The PRR provides for a transition plan to move the market from TCRs to CRRs, following implementation of the nodal market.
Chief Financial Officer Steve Byone reviewed the 2009 budget proposal, which the board will be asked to vote on at the next board meeting in May. The board’s Finance and Audit Committee has reviewed the budget three times and has recommended approval.
The proposed budget includes a $0.15 increase in the system administration fee, from the current $0.42 fee to $0.57 per megawatt hour.
Policy decisions driving the funding requirements include new functions necessary for nodal operations, primarily the cost for staffing new functions, adding new technology applications and facilities to house new staff and systems, and one-time items for nodal stabilization. Facilities requirements include space demands for staffing and data center space as required by the nodal market, and relocation of the Austin center due to lease expiration.
The system administration fee is assessed on wholesale energy transactions and becomes part of the overall cost of electricity. The approximate impact on an average household using 1000 kilowatt-hours/month would be $0.57 per month under the proposed budget. If including the nodal surcharge of $0.17 per MWh, which is expected to expire in 2013, the total approximate impact would be $0.74 per month.
If the budget is approved by the board in May, a fee case will be filed with the Public Utility Commission for review and approval.
Director of System Planning Dan Woodfin presented an update on the CREZ Transmission Report which was filed with the Public Utility Commission April 2. The PUC filing is available on the ERCOT Web site.
Other ERCOT staff report highlights included:
Information Technology Report (March performance metrics):
Board meeting documents are posted on www.ercot.com with the April 15 meeting agenda.
CEO Bob Kahn presented testimony at a joint hearing of the Senate Business and Commerce and Senate Natural Resources Committees on April 15. Kahn’s presentation “Planning for Texas’ Energy Future” is available on the ERCOT Web site.
| Contact | |
|---|---|
| Dottie Roark | 512-225-7024 |