PRR763
| Title: |
Use of WGRPP as Planned Operating Level in Day-Ahead Resource Plan for WGRs
|
| Next Group: |
|
| Next Step: |
|
| Status: |
Approved
on 06/17/2008
|
| Effective Date: |
07/01/2008
|
| Date |
Gov Body |
Motion |
Result |
Against |
Abstentions |
|
06/17/2008
|
Board of Directors
|
To approve PRR763 as recommended by TAC.
|
Passed
|
|
|
|
06/05/2008
|
TAC
|
To recommended approval of PRR763 as revised by TAC.
|
Passed
|
0
|
0
|
|
05/22/2008
|
PRS
|
To recommend approval of PRR763 as modified by PRS.
|
Passed
|
0
|
0
|
|
05/21/2008
|
PRS
|
To designate PRR-763, Use of WGRPP as Planned Operating Level in Day-Ahead Resource Plan for WGRs, for Urgent consideration
|
Passed
|
0
|
0
|
Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.
| Status: |
Approved
|
| Date Posted: |
05/16/2008
|
| Sponsor: |
John Dumas on behalf of the Reliability and Operations Subcommittee (ROS)
|
| Urgent: |
Yes
|
| Sections: |
2.1, Definitions, 2.2, Acronyms and 4.4.15, QSE Resource Plans
|
| Description: |
This Protocol Revision Request (PRR) allows Qualified Scheduling Entities (QSEs) representing Wind-powered Generation Resources (WGR) to use an ERCOT provided Wind-powered Generation Resource Power Potential (WGRPP) forecast as the planned operating level in the Resource Plan.
|
| Reason: |
Historically, ERCOT has not provided a wind-powered generation forecast for either the total ERCOT System or for the individual WGRs. Also, when performing RPRS studies, the planned operating level in the Resource Plans for WGRs is treated in the same manner as all other Resources. WGRs will continue to be treated in the same fashion; however, this PRR will allow ERCOT to perform Day Ahead RPRS procurement using a conservative forecast of the output from WGRs.
|