MIS LOG IN

PRR811

Summary

Title Real Time Production Potential
Next Group
Next Step
Status Approved on 01/19/2010

Action

Date Gov Body Action Taken Next steps
01/19/2010 BOARD Approved
01/06/2010 TAC Recommended for Approval ERCOT Board Consideration
11/05/2009 TAC Remanded TAC Review
10/20/2009 BOARD Remanded TAC Review
10/01/2009 TAC Recommended for Approval Board of Directors for consideration.
09/17/2009 PRS Recommended for Approval TAC Consideration
08/25/2009 PRS Recommended for Approval PRS IA Review
07/23/2009 PRS Recommended for Approval PRS Impact Analysis review
06/18/2009 PRS Deferred/Tabled PRS Consideration
05/21/2009 PRS Deferred/Tabled PRS Consideration

Voting Record

Date Gov Body Motion Result
01/19/2010 BOARD To approve PRR811 as recommended by TAC in the 1/6/10 TAC Report Passed
01/06/2010 TAC To recommend approval of PRR811 as recommended by TAC in the 10/01/09 TAC Recommendation Report as revised by the 12/22/09 WMS comments Passed
11/05/2009 TAC To remand PRR811 to WMS Passed
10/20/2009 BOARD To remand PRR811 to TAC. Passed
10/01/2009 TAC To recommend approval of PRR811 as recommended by PRS in the 9/17/09 PRS Recommendation Report. Passed
09/17/2009 PRS To endorse and forward the 8/25/09 PRS Recommendation Report and Impact Analysis for PRR811 to TAC Passed
08/25/2009 PRS To recommend approval of PRR811 as revised by PRS Passed
07/23/2009 PRS To recommend approval of PRR811 as amended by 7/22/09 WMS comments. Passed
06/18/2009 PRS To table PRR811 Passed
05/21/2009 PRS To table PRR811 for one month. Passed

Background

Status: Approved
Date Posted: Apr 17, 2009
Sponsor: Wind Coalition
Urgent: No
Sections: 2.1, 2.2, 6.5.1.1
Description: This Protocol Revision Request (PRR) establishes a requirement for Wind Generation Resources (WGRs) to telemeter a Real Time signal indicating the Real Time Production Potential which will be a function of wind and turbine availability at the time.
Reason: To provide ERCOT with information about the actual available wind generation for curtailed WGRs as well as additional information to tune the wind generation forecast models.

Key Documents

Related Content