MIS LOG IN

PRR795

Summary

Title 90-Day Transmission Outage Scheduling Timeline
Next Group
Next Step
Status Approved on 02/17/2009
Effective Dates
03/01/2009

Action

Date Gov Body Action Taken Next steps
02/17/2009 BOARD Approved
02/05/2009 TAC Recommended for Approval Board Consideration
01/22/2009 PRS Recommended for Approval TAC Consideration

Voting Record

Date Gov Body Motion Result
02/17/2009 BOARD Approve PRR795 as recommended by TAC. Passed
02/05/2009 TAC To recommend approval of PRR795 as recommended by PRS. Passed
01/22/2009 PRS To endorse and forward the PRS Recommendation Report and Impact Analysis for PRR795 to TAC. Passed

Background

Status: Approved
Date Posted: Jan 5, 2009
Sponsor: ERCOT
Urgent: Yes
Sections: 8.3.3
Description: This Protocol Revision Request (PRR): 1) Adds a new Outage response timeline that will place a requirement on ERCOT to coordinate Outages submitted with more than ninety (90) days notice at least seventy-five (75) days prior to the start of the proposed Outage; and 2) Provides clarification of three (3) to eight (8) day timeline to eliminate an overlap in requirements.
Reason: 1) The ERCOT TCR case development process incorporates Outages submitted a minimum of forty-five (45) days before their planned start. Currently, ERCOT has no obligation to review any Outage more than thirty (30) days prior to the start of the proposed Outage. The new timeline will increase the accuracy of the TCR Outage by assuring all Outages included in the monthly TCR model have been coordinated. 2) Original language was confusing in that it appeared that the first two (2) timelines overlapped each other.

Key Documents

Related Content