PRR596

Summary

Title Mothballed Generation Resource Estimated Return to Service Dates
Next Group
Next Step
Status Approved

Action

Date Gov Body Action Taken Next steps
No updates have been made to this issue.

Voting Record

Date Gov Body Motion Result
No updates have been made to this issue.

Background

Status: Approved
Date Posted: Apr 19, 2005
Sponsor: GATF
Urgent: Yes
Sections: 6.5.9.3
Description: This revision requires owners of Mothballed Generation Resources to provide annually to ERCOT projections of the MW of generation capacity of currently Mothballed Generation Resources that will return to service over the next five years.