MIS LOG IN

NOGRR234

Summary

Title Related to NPRR1098, Direct Current Tie (DC Tie) Reactive Power Capability Requirements
Next Group
Next Step
Status Approved on 03/31/2022

Action

Date Gov Body Action Taken Next steps
03/31/2022 PUCT Approved
03/07/2022 BOARD Recommended for Approval Revision Request Consideration
01/31/2022 TAC Recommended for Approval Revision Request Consideration
01/06/2022 ROS Recommended for Approval Revision Request Language
12/02/2021 ROS Recommended for Approval Impact Analysis Consideration
11/04/2021 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
03/31/2022 PUCT to approve NOGRR234 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization Passed
03/07/2022 BOARD to recommend approval of NOGRR234 as recommended by TAC in the 1/31/22 TAC Report Passed
01/31/2022 TAC to recommend approval of NOGRR234 as recommended by ROS in the 1/6/22 ROS Report Passed
01/06/2022 ROS to endorse and forward to TAC the 12/2/21 ROS Report and the Impact Analysis for NOGRR234 Passed
12/02/2021 ROS to recommend approval of NOGRR234 as amended by the 11/29/21 ERCOT comments Passed
11/04/2021 ROS to table NOGRR234 and refer the issue to the Operations Working Group (OWG) Passed

Background

Status: Approved
Date Posted: Sep 29, 2021
Sponsor: ERCOT
Urgent: No
Sections: 2.7.2, 2.7.3.3, and 2.7.3.6 (new)
Description: This Nodal Operating Guide Revision Request (NOGRR) revises the Nodal Operating Guide to be consistent with the Reactive Power capability requirements for Direct Current Ties (DC Ties) proposed by NPRR1098. A new Section 2.7.3.6, DCTO Responsibilities and DC Tie Requirements, is proposed to specify Direct Current Tie Operator (DCTO) responsibilities relative to Real-Time operational voltage control.
Reason: Regulatory requirements

Key Documents