MIS LOG IN

LPGRR027

Summary

Title Demand Response Revisions and Modification of Time-Of-Use (TOU) Schedule Approval Process
Next Group
Next Step
Status Withdrawn on 01/28/2008

Action

Date Gov Body Action Taken Next steps
01/28/2008 Withdrawn
09/25/2007 PWG Recommended for Approval PWG consideration of the Impact Analysis

Voting Record

Date Gov Body Motion Result
01/28/2008
09/25/2007 PWG To recommend to the COPS approval of this LPGRR as modified by the PWG. Passed

Background

Status: Withdrawn
Date Posted: Aug 8, 2007
Sponsor: Ernest Podraza
Urgent: No
Sections: 9.3 (new), 16, Appendix D, Acronyms and Glossary
Description: This Load Profiling Guide Revision Request (LPGRR) seeks to revise existing language for Demand Response (DR) programs implementation and to establish rules for assigning Profile Segments for Electric Service Identifiers (ESI IDs) on Demand Response programs. This LPGRR adds a new tab "DR Segment Assignment" to the attached Appendix D.
Reason: The Public Utility Commission of Texas (PUCT) issued a ruling on advanced metering which encourages DR for mass market Premises. Some Market Participants (MPs) are actively developing a pilot project for DR. These revisions are to meet the desired target implementation date of summer 2008 for DR functionality in ERCOT systems.